AHS Under Construction

AHS Under Construction
Construction Updates

Thanks to the passage of Ballot Issue 5B in November 2018, LOTS of improvements will be made to our building.




Phase 1: Summer 2019 - Dec. 2019
3rd Floor Remodel:

  • New furniture
  • New carpet
  • New paint
  • LED lighting
  • New bathroom fixtures
  • New ceiling tiles
  • Some walls removed to combine classrooms into larger rooms for cross-subject collaboration
  • New flooring and seating in the Black Box Theatre

Update as of Dec. 18, 2019 - phase 1 is almost complete. Furniture will be moved in soon and classrooms will be ready for the Spring 2020 semester.
3rd floor double classroom Remodeled Black Box theater 3rd floor remodeled restroom

Phase 2A:  12/30/19 -  3/20-20
1st floor B Hall remodel
All classrooms except 4 science rooms

Phase 2B: 3/23/20 - 5/21/20
Remodel of 2 science classrooms, 2nd floor bridge classrooms and 2nd floor B Hall classrooms

Update as of April 24: Construction is ahead of schedule. This is the new Creative Learning Space (Smart Lab):
 CLS Lab CLS Lab

Phase 2C: 5/21/20-7/31/20
Remodel of all walkways, C wing, 2 more science classrooms, weight room, green room, public bathrooms and 2nd floor A wing.

Photos as of July 30, 2020:
Summer 2020 renovations Summer 2020 renovations Summer 2020 renovations Summer 2020 renovations
Auxilary Gym: 1/3/20-9/18/20

  • New auxilary gym to be built on the west side of the current large gym
  • New elevator to provide access to the gym
Ribbon Cutting August 2020!